MA’ADEN – Taswia Sulfur Derivatives Plant – Initial Site Work

ITEAC contributed to the early development of the Taswia Sulfur Derivatives Plant by supporting critical initial site work activities across an area of approximately 50,000 m².

The scope included comprehensive site preparation, rough grading, subgrade compaction, construction of temporary roads, establishment of a construction laydown area, and installation of security fencing and gates, all aligned with the latest industrial security standards.

Detailed surveying, soil proof rolling, backfilling, and compaction were completed following strict quality testing protocols to ensure a solid foundation for future plant construction.

Location: Al Jubail Secondary Industrial Area, Section “K”, Block 12, Lot 4